The next phase of Ottawa's expanding light rail transit system is once again behind schedule, with transit staff suggesting the north-south Trillium Line will open sometime between July and September.
Add Yahoo as a preferred source to see more of our stories on Google. A Trillium Line train departs Bayview station on Dec. 6, 2024, the same day OC Transpo announced a phased-in opening for the ...
The Trillium Line has cleared its biggest hurdle, successfully completing a 14-day trial run it had to pass before the city would accept its newest light-rail transit line. “As the future maintainer ...
The Trillium Line begins what could be the last two days of trial running this weekend, having scored a 99.4 per cent reliability on Thursday, Day 11 of the 14-day trial run. The city has set 98.5 per ...
Add Yahoo as a preferred source to see more of our stories on Google. Alta Vista Coun. Marty Carr, left, and River Coun. Riley Brockington, right, take part in a ribbon-cutting ceremony at Walkley ...
More than two months after it opened to the public, Ottawa's north-south Trillium Line will be open seven days a week, starting this coming Sunday, March 16. An expanded and renamed Line 2 to ...
The City of Ottawa says final testing of the north-south Trillium light rail line will begin this coming Monday — meaning the earliest the line could open to riders is mid-November. Transit services ...
Passengers could be riding the Trillium Line O-Train as early as mid-November if testing goes well on the long-delayed LRT extension. Transit general manager Renée Amilcar announced Thursday that ...